Article 43 - Procurement Proposals and MRP

Article 43 - Procurement Proposals and MRP


Article 43: What procurement proposals does MRP generate and how do I process them?

What procurement proposals can MRP create?

When MRP identifies a material shortage, it automatically generates procurement proposals - recommendations for specific actions to resolve the shortage.

What are the main types of procurement proposals?

Purchase Requisitions

When generated:

  • Material has procurement type "F" (External)
  • Vendor sourcing is the preferred method
  • Lead time and cost favor external procurement

What information is included:

  • Material number and description
  • Required quantity to cover shortage
  • Delivery date needed
  • Suggested vendor (if source list exists)
  • Cost center or account assignment

How to process:

  1. Review requirements in MD04 or MD05
  2. Verify quantities and delivery dates
  3. Convert to Purchase Order via ME57 or ME59
  4. Send to vendor for fulfillment

Planned Orders

When generated:

  • Material has procurement type "E" (In-house)
  • Internal production is preferred method
  • Manufacturing capability exists

What information is included:

  • Material to be produced
  • Production quantity needed
  • Start and finish dates
  • BOM and routing references
  • Resource requirements

How to process:

  1. Review production capacity and scheduling
  2. Firm the planned order if approved (MD11)
  3. Convert to production order (CO40)
  4. Release for production when ready

Transfer Requirements

When generated:

  • Material sourced from another plant or storage location
  • Special procurement key configured for transfers
  • Stock available at source location

Processing steps:

  1. Verify source availability
  2. Create transfer order or stock transport order
  3. Coordinate logistics between locations
  4. Monitor transfer until receipt

How do I efficiently process multiple proposals?

Mass Processing Tools

Transaction ME57 (Convert PRs to POs):

  • Bulk conversion of purchase requisitions
  • Automatic vendor selection based on source determination
  • Exception handling for complex cases

Transaction MD11 (Firming Planned Orders):

  • Mass firming of planned orders
  • Capacity checking integration
  • Priority-based processing

Transaction MD15 (Collective Conversion):

  • Mixed proposal types handled together
  • Planner-specific workload management
  • Exception reporting for failed conversions

What factors should I consider before converting?

Before Converting Purchase Requisitions:

Supplier Evaluation:

  • Vendor capacity to deliver on time
  • Price competitiveness and terms
  • Quality capability and certifications
  • Current workload and priority

Internal Considerations:

  • Budget approval and authorization
  • Delivery coordination with receiving
  • Quality inspection requirements
  • Payment terms alignment

Before Converting Planned Orders:

Production Feasibility:

  • Manufacturing capacity availability
  • Component availability from BOM
  • Resource scheduling and conflicts
  • Quality requirements and setup time

Strategic Alignment:

  • Make vs buy economics
  • Load balancing across work centers
  • Inventory strategy and turnover goals
  • Customer priority and delivery promises

What monitoring is needed after conversion?

Purchase Order Monitoring:

  • Vendor confirmations and delivery updates
  • Expediting for critical requirements
  • Quality issues and corrective actions
  • Invoice verification and payment

Production Order Monitoring:

  • Material availability for production start
  • Progress reporting and milestone tracking
  • Quality control and testing results
  • Goods receipt upon completion


    • Related Articles

    • Article 38 - MRP

      Article 38: What is Material Requirements Planning (MRP) in SAP? What is MRP? Material Requirements Planning (MRP) is the core planning engine in SAP that ensures material availability by automatically balancing supply and demand. It calculates ...
    • Article 40 - MRP Types

      Article 40: What are the different MRP types and procurement keys? What are MRP Types? MRP Types are configuration codes that determine how the MRP run behaves for each material. They control the planning logic, procurement method, and calculation ...
    • Article 42 - MRP Results

      Article 42: How do I interpret MRP results and shortage situations? How do I read MRP results? MRP results show you a time-phased view of supply and demand for each material, highlighting when shortages will occur and what procurement actions are ...
    • Article 57 - MRP Controllers

      Article 57: How do SAP Fiori apps help MRP controllers and planners? What planning and MRP capabilities do Fiori apps provide? Fiori apps revolutionize materials planning by providing visual, interactive tools that help MRP controllers quickly ...
    • Article 39 - How MRP Runs

      Article 39: How does the MRP run process work step-by-step? What happens during an MRP run? The MRP run is a systematic calculation process that evaluates each material individually to determine if procurement action is needed. It follows a logical ...